    Question 1.1.Which is a key benefit of the Control Cost process? (Points : 9)
    Provides the means to recognize variance from the plan in order to take corrective action
    Approves changes to the budget
    Assures the project will not overrun the budget
    Makes changes to the Project Management Plan
    Question 2.2.Actual cost is: (Points : 9)
    the authorized budget assigned to scheduled work.
    the realized cost for the work performed.
    the activity amount before any reserves are included.
    a measure of the work performed expressed in terms of the budget authorized for that work.
    Question 3.3.There is (are) _________ way(s) to calculate the EAC. (Points : 9)
    four
    two
    three
    one
    Question 4.4.What should be used if EVM is not being used? (Points : 9)
    Actual costs
    Planned costs
    Budgeted costs
    Analysis of the cost baseline against actual costs for the work performed
    Question 5.5.If earned value (EV) = 450 actual cost (AC) = 500 and planned value (PV) = 425 what is cost performance index (CPI)? (Points : 9)
    1.11
    0.85
    0.9
    1.18
    Question 6.6.If earned value (EV) = 450 actual cost (AC) = 500 and planned value (PV) = 425 what is schedule performance index (SPI)? (Points : 9)
    1.11
    0.94
    0.9
    1.05
    Question 7.7.One way to calculate the estimate at completion (EAC) is to divide the budget at completion (BAC) by the __________. (Points : 9)
    (CPI*SPI)
    TCPI
    SPI
    CPI
    Question 8.8.Perform Quality Assurance is in the __________ Process Group: (Points : 9)
    Monitoring and Controlling
    Closing
    Executing
    Planning
    Question 9.9.Which is a key benefit of the Perform Integrated Change Control process? (Points : 9)
    Makes changes to the project management plan
    Allows stakeholders to understand the state of the project
    Prepares deliverables for acceptance
    Reduces risk
    Question 10.10.Configuration identification management activities are included in the__________ process: (Points : 9)
    Perform Integrated Change Control
    Validate Scope
    Control Scope
    Collect Requirements
    Question 11.11.Processes in which of the following Project Management Process Groups produce change requests? (Points : 9)
    Planning
    Initiating
    Executing
    All of the above
    Question 12.12.A __________ is used to document changes that occur during the project. (Points : 9)
    change log
    change control board
    change baseline
    change request
    Question 13.13.Administrative closure of the project includes all of the following except: (Points : 9)
    activities to collect project records
    release resources
    actions and activities to satisfy completion criteria
    actions to transfer the projects products to the next phase
    Question 14.14.The projects cost of changes typically: (Points : 9)
    increases as the project time increases
    stays the same during the project time
    decreases as the project time increases.
    peaks in the middle of the project time.
    Question 15.15.The key benefit of the Control Scope process is it: (Points : 9)
    accepts deliverables.
    verifies deliverables
    allows the scope baseline to be maintained
    reduces rework.
    Question 16.16.Change requests outputs from Validate Scope for defect repair are: (Points : 9)
    sent directly to the Direct and Manage Project Work process.
    reviewed in the Quality Control process.
    reviewed in the Perform Integrated Change Control process.
    reviewed in the Quality Assurance process.
    Question 17.17.The organizational process assets that can influence the Control Scope process include the following except: (Points : 9)
    informal scope control-related policies
    monitoring and reporting templates
    formal scope control-related policies
    variance analysis
    Question 18.18.Fast tracking is a technique used to shorten the schedule by: (Points : 9)
    reducing scope
    changing the critical path
    doing tasks in parallel
    adding resources
    Question 19.19.Schedule performance reviews include all of the following except: (Points : 9)
    critical path method
    crashing.
    trend analysis
    earned value management
    Question 20.20.Change requests outputs from Control Scope process are: (Points : 9)
    reviewed in the Perform Integrated Change Control process.
    reviewed in the work performance data.
    reviewed in the Quality Assurance process.
    sent directly to the Direct and Manage Project Work process.